List of approval of investment policy projects


 

LIST OF APPROVAL OF INVESTMENT POLICY PROJECTS RESEARCH FOR PLANNING FOR 2021

* First quarter

1. Car and service showroom project in Hiep Hoa commune, Quang Yen town

- Investor: Dong Bac Medicinal Plantation, Production and Processing Co., Ltd

- Location of project implementation: in Cai Tan village, Cong Hoa commune, Cam Pha city

- Total expected investment capital:  VND 13.900 million

- Total land use area: 4000 m2

- On March 24, 2020, the Party Committee of the Provincial People's Committee issued Notice No. 137-TB/BCSD agreeing to report to the Standing Provincial Party Committee to approve the NCQH location.

* Second quarter

1. Project of Headquarters Area, staff dormitory and general service business area

- Investor: Southeast Asia Logistic Joint Stock Company

- Project implementation location: in Thong Nhat commune, Ha Long city, Quang Ninh province

- Total estimated investment capital:  VND 50.000 million

- Total land use area: 60000m2

- Decision 1496/QD-UBND dated May 8, 2020 of the Provincial People's Committee approving the location of the project NCQH

2. Concentrated organic production industrial cluster project

- Investor: Viet Dung Investment Consulting Joint Stock Company

- Project implementation location: at Vu Oai commune, Ha Long city

- Total estimated investment capital:  VND 215.048 million

- Total land use area: 700000m2

- Decision No. 1471/QD-UBND dated May 7, 2020 of the Provincial People's Committee approving the location of the NCQH project

3. Vinpearl Safari Ha Long Nature Conservation and Ecotourism Complex Project

- Investor: Vinpearl Joint Stock Company

- Project implementation location: at Vu Oai, Hoa Binh, Ky Thuong, Dong Lam communes, Ha Long city

- Total estimated investment capital:  VND 200.000 million

- Total land use area: 11350000 m2

- Decision No. 2111/QD-UBND dated June 24, 2020 of the Provincial People's Committee approving the location of the project's NCQH; Decision No. 2598/QD-UBND dated July 28, 2020 of the Provincial People's Committee;

* Third quarter

1. Urban complex project market, tourism, commercial services

- Investor: Joint venture between Geleximco Group and Ha Thanh Import-Export Company

- Project implementation location: Le Loi commune, Ha Long city

- Total estimated investment capital:  VND 5.981.000 million

- Total land use area: 2800000m2

- Decision No. 2403/QD-UBND dated July 16, 2020 of the Provincial People's Committee approving the location of the project NCQH

2. Western Man River urban area

- Investor: HL Ha Long Joint Stock Company

- Project implementation location: Le Loi commune, Ha Long city

- Total estimated investment capital:  VND 2.738.000 million

- Total land use area: 1411000m2

- Decision approving the location of NCQH No. 2241/QD-UBND dated July 3, 2020 of the Provincial People's Committee

3. High quality Lan Ho Diep production zone project

- Investor: Tin Phat Thong Nhat Cooperative

- Project implementation location: Ha Long city

- Total expected investment capital:  VND 32.000 million

- Total land use area: 80000m2

- Decision No. 2242/QD-UBND dated July 3, 2020 of the Provincial People's Committee approving the NCQH location

4. Phong Hai New Urban Area Project

- Investor: Hai Phat Real Estate Investment and Trading Company

- Project implementation location: Phong Hai, Quang Yen town

- Total expected investment capital:  VND 2.450.000 million

- Total land use area: 440000m2

- Decision No. 3525/QD-UBND dated September 10, 2020 of the Provincial People's Committee approving the NCQH location

5. Planting medicinal plants and high quality clean vegetables

- Investor: Dong Nam Mineral Joint Stock Company

- Location of the project: at the cassava hill area, Mao Khe ward, Dong Trieu town

- Total estimated investment capital:  VND 20.000 million

- Total land use area: 210000m2

- Decision No. 4469/QD-UBND dated July 2, 2020 of the Provincial People's Committee approving the NCQH location

6. Cam Son New Urban Area Project, Cam Pha City

- Investor: TANA Construction Investment and Trading Joint Stock Company

- Project implementation location: Cam Son, Cam Pha city

- Total estimated investment capital:  VND 1.314.000 million

- Total land use area: 954000 m2

- Document No. 5571/UBND - QH2 dated August 13, 2020: content assigned to Cam Pha City People's Committee to chair

7. Urban tourist resort complex project in the West port of Mui Chua

- Investor: Flamingo holding group JSC

- Project implementation location: Tien Yen

- Total expected investment capital:  VND 4.800.000 million

- Total land use area: 15500000 m2

- Document No. 5394/UBND-QH2 dated August 10, 2020 of the Provincial People's Committee approving the NCQH location

8. Residential Area Cam Phu Ward, Cam Pha City

- Investor: Joint venture between HDC Hanoi Joint Stock Company and Licogi Corporation – JSC

- Project implementation location: Cam Phu ward, Cam Pha city

- Total expected investment capital:  VND 219.000 million

- Total land use area: 41000m2

- Decision No. 3656/QD-UBND dated September 22, 2020 of the Provincial People's Committee approving the NCQH location

* Fourth quarter

1. Agriculture and Forestry Production Farm VAC Hoanh Bo

- Investor: Quang Ninh Park Greenery Joint Stock Company

- Project implementation location: Hoanh Bo

- Total estimated investment capital:  VND 28.000 million

- Total land use area: 1020000m2

- Decision No. 7747/QD-UBND dated November 12, 2020 of the Provincial People's Committee approving the NCQH location

2. Kaolin-Pyrophylite mining project of ore body I, IB

- Investor: Quang Ninh Import-Export and Investment Joint Stock Company

- Project implementation location: in Quang Son commune, Hai Ha district, Quang Ninh province

- Total estimated investment capital:  VND 18.100 million

- Total land use area: 232900m2

- Document No. 6736/UBND-QH2 dated October 3, 2020 of the Provincial People's Committee approving the NCQH location

3. Urban areas and public services

- Investor: Construction Joint Stock Company 545

- Project implementation location: in Ha Phong ward, Ha Long city

- Total estimated investment capital:  VND 1.000.000 million

- Total land use area: 280000m2

- Document No. 6818/UBND-QH1 dated October 6, 2020 approving the delivery of Ha Long City

4. Central Park Urban Area

- Investor: Van Phu Investment Joint Stock Company - Invest

- Project implementation location: in Le Loi commune, Ha Long city

- Total estimated investment capital:  VND 1.650.000 million

- Total land use area: 740000m2

- Decision No. 3825/QD-UBND dated October 7, 2020 of the Provincial People's Committee approving the location of NCQH

5. Complex of cultural tourism center and marine eco-urban center

- Investor: Van Phu Investment Joint Stock Company - Invest

- Project implementation location: in Thong Nhat commune, Ha Long city

- Total expected investment capital:  VND 309.000 million

- Total land use area: 2600000m2

- Decision No. 3857/QD-UBND dated October 8, 2020 of the Provincial People's Committee approving the NCQH location

6. Urban tourism in Le Loi commune, Ha Long city

- Investor: Dong A International Group Joint Stock Company and MBLand - Golden Star Investment Joint Venture (representative of MBLand Corporation and Vietnam Gold Star Real Estate Joint Stock Company)

- Project implementation location: in Le Loi commune, Ha Long city

- Total estimated investment capital:  VND 212.000.000 million

- Total land use area: 890000m2

- Decision No. 3901/QD-UBND dated October 9, 2020 of the Provincial People's Committee approving the location of NCQH

7. Garment Factory Project

- Investor: Hoa Loi Dat Garment Co., Ltd (Vietnam)

- Location of the project: in Vo Ngai commune, Binh Lieu district

- Total expected investment capital:  VND 913.000 million

- Total land use area: 158000m2

- The Provincial Party Committee of the Provincial People's Committee reports to the Provincial Standing Committee

The committee approved the plan at Document No. 553-CV/BCSD dated October 26, 2020

8. Dong Trieu golf course business service area project

- Investor: Silk Path Golf Course Joint Stock Company

- Project implementation location: in An Sinh commune, Dong Trieu town

- Total expected investment capital:  VND 741.000 million

- Total land use area: 1340000m2

- Document No. 8089/UBND-QH1 dated November 25, 2020 of the Provincial People's Committee approving the NCQH location

9. FPT Middle School and High School Project

- Investor: FPT Education Co., Ltd

- Location of the project: in Cao Xanh ward, Ha Long city

- Total expected investment capital:  VND 241.000 million

- Total land use area: 12900 m2

- Decision No. 4361/QD-UBND dated November 23, 2020 of the Provincial People's Committee, assigning the People's Committee of Ha Long City to make the National Assembly

10. Urban area project in the Southeast of Dam Ha town

- Investor: Thien Thai Hotel and Tourism Joint Stock Company (ARIYANA)

- Project implementation location: Dam Ha town, Dam Ha district

- Total estimated investment capital:  VND 210.000 million

- Total land use area: 65000 m2

- Decision No. 4807/QD-UBND dated December 28, 2020 of the Provincial People's Committee, assigning the People's Committee of Ha Long City to make the National Assembly