INFRASTRUCTURE INVESTMENT PROJECTS FOR INDUSTRIAL PARKS
SOUTH TIEN PHONG INDUSTRIAL PARK
Location: Within Dam Nha Mac Industrial – Service
Park, in the Southern portion of Tien Phong
commune, Quang Yen district-level town, Quang
Ninh province, Vietnam
Area: 487.4 ha
Employer: Tien Phong Industrial Park Joint Stock
Company
Address: No.8-9 D My Gia, Vinhomes Dragon Bay
Urban Area, Ha Long City, Quang Ninh
Characteristics: Being a multi-sector industrial Power supply: Construction of 110/22kV-(40+63) MVA
development zone, synchronously invested with substation for separate power supply. High-voltage
necessary technical infrastructures, operational connection is carried out on 110kV power line from
center, service port, synchronous system of auxiliary Cho Roc to Cat Hai. In the future a 100kV power line
works in accordance with the goals of environment from Khoai River 220kV substation to the area shall be
protection and to ensure biophysical environment, arranged according to the province’s power planning.
meeting requirements of fire protection, bringing
convinence and safety to the investors, as well as General wastewater treatment station: Capacity of
in harmony with surrounding areas. Infrastructure 10,000 m3/day.
system, port facilities are arranged to serve the Waste treatment: Classification of primary solid
industrial park, along with warehouses and logistics, wastes (CTRs) is carried out at the source of emission.
general utilities, standard workshops, harbors to Classification of secondary CTRs is carried out at
receive anchored ships, storages, yards. concentrated classification areas. The wastes are
Interal transport: Being designed in squares with stored during the day and shall be transported to
distance between the primary roads is 600-1000m, the concentrated treatment area at the end of the
distance between the branch roads is 300-450mm day. CTRs of the industrial park, after being collected,
Water supply: Using water from Yen Lap plant. shall be transported to the province’s concentrated
treatment area under the planning.
Construction of booster pumping station with a
capacity of 12,000m3/day. Communications: Construction of Chanh River
satellite station
24 Quang Ninh Economic Zone Authority